Case Study – Home Extension

Snug Home Extension Kit Case Study - March 2017

STAGE 1: Extension Structure Build

* The foundations were completed prior to the start of the Snug Home Extension build.

DAY 1: Monday 8am

Snug supplied treated base rail installed on existing slab ready to receive tailor made Snug fully insulated structural extension kit. First panel fitted 20 minutes later.

Day 1: Monday 11.45am

All structural wall panels fitted, openings preformed and trimmed. Snug supplied bi-fold door goal post integrated and thermally broken. Panels all screwed up airtight. Wall plate fixed for roof.

Day 1: Monday 3.30pm

Roof panels installed ready for the roofer, Window fitting first fix plumber / electrician.

Stage 1 Completed

Snug Home Kits structure build is finished after 1 day

100%

Overall Snug Home Extension Progress

25%

Request an Estimate

Embrace the simplicity of a Snug Home Kits & talk to one of our advisers and request an estimate for a Home Extension

STAGE 2: Roof & Doors

Day 3: Wednesday 11.20am

Roof tiles on (traditional concrete), broken through to existing structure, electrical and plumbing first fix in and drylining started. Bifold doors and windows in.

Stage 2 Completed

Snug Home Kits extension build is finished after 3 days

100%

Overall Snug Home Extension Progress

47%

Day 6: Sunday 4.00pm

Floor insulation and screeds were done by the weekend.

STAGE 3: Kitchen Interior

Day 16: Sat 5.00pm – Full Completion of Interior

Full completion including the finished Kitchen diner was completed within 10 further days.

Stage 3 Completed

Interior is complete and ready to use.

100%

Overall Snug Home Extension Progress

100%